Home·Sample sites

Sample sites

A public preview of DC Plug's site ladder. Pick a tier below to see exactly what it delivers, then a sample site: one Prime, one Strong, one Watch, real named plants scored by the engine.

Sample library
New York · NYISO

Indian Point 3

83
Composite
PrimeNo power constraintreadiness 92· 87% confidence

Decommissioned nuclear plant on NYISO with full power availability, an on-site 345 kV interconnection, and a large build-ready parcel. Prime tier with no power constraint; community and political sentiment is the weakest input.

Grid difficulty · hard

In this county, 9% of power projects got built (2 of 23 resolved), versus about 17% nationally.

County power · market time-to-power not assessed · headroom unknown

County/market-level screening read, not a utility will-serve confirmation or a Phase 1 ESA.

Top 3 risks to clear
  • Community and political (35)
    Local jurisdiction posture not fully assessed, confirm locally.
  • Fiber and latency (38)
    Confirm fiber and latency meet your workload requirement.
  • Zoning and permitting (60)
    Confirm local zoning allows data-center use at this parcel.
Questions to ask before you commit
  • Is the existing interconnection agreement assignable, and at what MW?
  • What is the site's real deliverable power versus nameplate?
  • Any active local moratorium or zoning constraint on data-center use?

Not assessed for this site: Land / parcel, Land cost, Incentives.

Verified facts
Existing grid interconnectionyes
Former plant nameplate1,012 MW
Grid voltage at POI345 kV
Power cost (wholesale)4.353 c/kWh
Streamflow at nearest gage1,100 cfs
Evidence in the Deal Pack
Substation
BUCHANAN 345 kV, 0.5 mi
Substation
Unnamed substation 138 kV, 0.7 mi
Serving utility
Consolidated Edison Co-Ny Inc (Consolidated Edison)
Parcel of record
Temporarily unavailable: the underlying parcel data source is being restored, for every Deal Pack right now, not gated by tier.
Additional site intelligence
Power-path optionality: 13 substations in reach, nearest banks at 345/138 kV. Supports the 2N (dual substation) redundancy this load size typically expects.
Water-source optionality: 39 surface-water sources in reach (cooling-supply candidates). Volume and water rights are assessed at diligence.
Wildfire hazard (county): Very Low
Earthquake loss risk (county): Relatively Moderate
Seismic design category: B
Nearest dam: Lounsbury Pond Dam, Significant-hazard, 1.4 mi
High-hazard dams within 6 mi: 8
Wetland share of parcel (approximate): 32.7%
Public water service area: outside a mapped service area
Nearest solar farm: CBP Solar, 1.8 MW AC, 0.5 mi
Nearest wind turbine: unknown, Kings County, 42 mi
Renewables PPA optionality: 57 solar / 0 wind projects in reach, potential PPA counterparties.
Large-load regulatory readiness: Gated (as of 2026-06-30)
Nearest major road: 9 mi
Nearest local road: Broadway, 0.4 mi
Nearest mainline rail: 0.9 mi
Nearest submarine cable: Seabras-1, 38.5 mi
Design wet-bulb temperature (approximate): 73.2°F
Terrain / slope: moderate (7.35%)
Regional interconnection-cost benchmark: $97/kW median (n=294 projects)
Download a full sample Deal Pack (PDF) →

A real Deal Pack on a sample powered site, the actual deliverable, one you can forward internally.

Estimated deliverable capacity
🔒deliverable MW held · 87% confidence
A modeled screening estimate, the figure is in the full read.
Full dimension breakdown, with confidence
power dimension
Power availability
100
Interconnection
100
Transmission
86
Power cost
77
Reliability and carbon
71
Environmental
90
Water
95
Natural hazard
80
Climate and cooling
85
Zoning and permitting
60
Community and political
35
Fiber and latency
38
Power: clear. Strong on every power dimension, so nothing here holds the composite back.
Diligence read
Advance to diligencedeliverable MW held
$13.0M / MW
Capex (benchmark)
🔒 held
Total build (modeled)
🔒
Months to energize
In the full build
pending deal terms
IRR
Federal ITC: 30% on on-site energy property
State incentive: none curated for this state
What could derail it: Community and political (35), Fiber and latency (38)

Capex, ITC, and build figures are labeled public-benchmark assumptions, not quotes. IRR is left uncomputed until real lease or PPA terms are supplied, revenue is never invented.

Solution hooks

No solution gap flagged on this site: power and cooling-water both come back clean.

Every gap the Deal Pack diagnoses gets a held solution hook. The answer, the route and the specifics, is the paid engagement.

Evidence and filings
  • Interconnection status on file
  • Retirement and capacity records on file
  • Regulatory filings tracked for this footprint

Every fact is cited. Data provenance is disclosed to the buyer under NDA.

Regulatory signals
  • MED2026-06-23 · National
    US sees record Q1 2026 energy-storage installations

Detected and triaged automatically, refreshed nightly.

The route, the enabling supply, and the schedule for every gap this Deal Pack flagged are engineered in the full build.Scope the full build →
That was one site, in full

DC Plug ranks the whole country, and the sites you already track.

  • →Every powered site nationally, ranked and refreshable
  • →Your own candidate sites, scored the same way
  • →The full emerging-sites watchlist, not just five
  • →Live grid and regulatory feeds, refreshed nightly
  • →Per-site diligence on any site you pick
  • →The ranked map and sortable shortlist

A commercial platform, not a free signup. Book a demo to run it on your pipeline.

Book a demo→